By National Wind Watch Altering a wind farm’s construction timeline is an “amendment,” and a proposal for a 91-turbine farm must return to state regulators for an extension, potentially subjecting the facility to stricter state rules, the Ohio Supreme Court ruled today. The Supreme Court voted 5-2 that the Ohio Power Siting Board improperly approved a request by developers of the Black Fork Wind Energy Project to extend the date to begin construction from January 2017 until January 2019. Opponents of the farm, which . . .