A challenge by a Kingscourt farmer against An Bord Pleanála’s ruling that a high-voltage underground cable connecting a €21 million wind farm to the national grid does not need planning is to be fast-tracked before the Commercial Court. Val Martin from Gortnakesh, who owns lands close to the under-construction windfarm at Raragh, Kingscourt, is challenging a decision by the planning authority, which deemed a 20-kilovolt cable connecting the development and an ESB substation at Kilaulun, Co Meath as “exempted”. “The . . .