Optimized turbine installation saves wind farm time and money

By Michelle Froese Mammoet Wind’s integrated approach saved almost two days of installation time per turbine at Juktan wind farm in Sweden.
Mammoet Wind, the turnkey solution provider for the wind energy industry, has successfully installed nine Siemens wind turbines at the Juktan wind farm in Blaiksjön, Sweden.
Project owner Vattenfall contracted Mammoet to do the entire scope of the Juktan project, including shipping, onshore transportation, crane operations, and mechanical and electrical installation. By managing the entire project, Mammoet Wind was able to optimize the whole process and deliver all nine turbines two weeks ahead of schedule – saving time and money for the client.
The

Read Full Article Here

For more great articles: Windpower Engineering & Development