Town discusses possible Antrim Wind construction extension #NH

By National Wind Watch Antrim select board members continued to hash out a potential construction-extension agreement between the town and an energy company that is looking to build nine wind turbines along Tuttle Hill. Antrim Wind Energy has proposed a one-time payment of $100,000 in exchange for an extension on its commercial operation date. The payment could extend the company’s commercial operation date from Dec. 31, 2018 to the same day the following year. Already the energy company has agreed to pay the town . . .